Following the completion of crane service works over the holidays, construction progress has continued at a good pace. During this time, necessary modifications to Phase 3 structural plans were resubmitted to planning and approved, and are now underway. Interior works have continued in Phase 1 and 2, and significant progress has been made on the internal MEP.

 
 
 
 

CONSTRUCTION PROGRESS

PHASE ONE

  • Structure is complete, secured and prepared for fit out

  • Glass windows and doors have been installed and sealed

  • MEP works are ongoing throughout

  • Work safety rails currently being inspected and reinforced

 
PHASE TWO

  •  Structure has now been completed up to the top floor and some glazing has been installed

  • Work safety rails are currently being inspected and reinforced throughout

  • MEP works are ongoing throughout

  • Pool rough-in works are in progress

PHASE THREE

  • Staircase 1 has been poured up to the second floor level

  • Elevators 2 and 3 - shafts have been poured up to the second floor level

  • All first floor and pool deck columns have been poured

  • MEP rough-in’s were completed prior to concrete pours

  • Second floor beams and slab deck are currently being formed

  • MEP works are currently ongoing throughout second floor beams and slab deck

  • Staircase 2 has been formed and rebar works are nearing completion, with concrete to be poured this week.

  • Most of the ICF walls have been formed and poured up to second floor level

  • Remaining first floor ICF walls to be poured within the next two weeks

  • Third floor columns are currently being erected in the North section of Phase 3

  • Second floor concrete beams and slab scheduled to be poured mid-May

  • Staircase 1 and second floor, south shear walls are scheduled to be poured at the end of May

  • Third floor beams and concrete slab scheduled to be poured in the second week of June