The progress on the site at Kailani has been moving at a steady pace across all three phases. The next process will be moving onto the second floor of Phase 2; observers can look forward to seeing Phase 2 going vertical and out the ground.

CONSTRUCTION PROGRESS

PHASE 1

  • All site utility works have been completed. Arrival of windows scheduled for June 2021

PHASE 2

  • Continuing to work on beams and decking, including the walls in Unit 104

  • Forming up deck at 27’-1” elevation on second floor

  • Presently building the staircase shaft

  • All boxes hung in position in relation to core area, MEP and formwork

 PHASE 3

  • Construction work to commence on pool foundation

  • Currently forming and pouring entrance and exit ramps

  • Ongoing works on the footing and pads on the south side