Construction Update: April 2022
The progress on the site at Kailani has been moving at a steady pace across all three phases. The next process will be moving onto the second floor of Phase 2; observers can look forward to seeing Phase 2 going vertical and out the ground.
CONSTRUCTION PROGRESS
PHASE 1
All site utility works have been completed. Arrival of windows scheduled for June 2021
PHASE 2
Continuing to work on beams and decking, including the walls in Unit 104
Forming up deck at 27’-1” elevation on second floor
Presently building the staircase shaft
All boxes hung in position in relation to core area, MEP and formwork
PHASE 3
Construction work to commence on pool foundation
Currently forming and pouring entrance and exit ramps
Ongoing works on the footing and pads on the south side
Claire Johnston