Construction Update: October 2021
Construction on the Kailani site continues to advance; the Phase 2 structure has progressed to the 5th floor level and the team is continuing works on the Phase 3 basement. The fit out of the hotel’s model room is in process and ongoing.
CONSTRUCTION PROGRESS
PHASE 1
This structure has been completed. The windows are currently on site and awaiting installation for further approval
Construction of Phase 1’s concrete slab canopy over the entry doors is now completed
PHASE 2
Concrete pour of the 5th floor slab is scheduled for later in the month of October
The 3rd floor walls have been completed
The staircase’s mechanical, electrical and plumbing works are roughed in up to the 5th floor level
The model room’s stud framing is completed. Awaiting the installation of glass door for waterproofing and drywall installation
All common partition walls for the units are now framed
Staircase is formed from 4th to 5th floor and concrete pour scheduled for this month
PHASE 3
This area is graded and four catch basins have been installed
The installation of electrical conduits is to commence this month
Ramps #1 and #2 have been poured
Grease/oil interceptor #2 has been installed beneath Phase 3’s basement floor