Construction Update: October 2022

Claire Johnston
Construction Update: October 2022
 

Construction on the Kailani site continues to move along at a steady pace. Phase Three basement and first floor levels have now been completed. The building structure up to the top floor is complete, MEP works are currently ongoing throughout and the main pool structure has also been finished, along with the adjacent pond feature on the pool deck.

 
 
 
 

CONSTRUCTION PROGRESS

PHASE ONE

  • Structure is complete, secured and prepared for fit out

  • Glass windows and doors have been installed and sealed

  • MEP works ongoing including lightning protection

  • Ancillary works are completed to just below grade level

 
PHASE TWO

  • Structure is now completed up to the seventh-floor level, secured and prepared for MEP services installation

  • Units 104, 401 and 601 pool containment walls have been poured

  • MEP cans, block outs and sleeves are installed throughout along with main service infrastructure

  • Ancillary works are completed to just below grade level

  • Unit 202 model room fit out is now complete and is available for viewing purposes

 
PHASE THREE

  • The structural works are progressing well. Walls and floors have all been poured in the basement parking garage, main electrical room, kitchen, mechanical room and staff room

  • The main pool structure is now complete along with the adjacent pond feature on the pool deck

  • MEP works are progressing very well

  • Basins for emergency flood water ejection have been put in place in key areas of the basement parking lot

  • The first-floor slab is now 100% complete and preps have been made for the erection of columns and walls leading up to the second floor