Construction on the Kailani site continues to move along at a steady pace. The Phase 2 structure has advanced to the seventh floor level and the team is continuing works on the Phase 3 basement. The fit out of the hotel’s model room is currently in process and ongoing. Ancillary works surrounding the structure are also progressing well.

 
 

CONSTRUCTION PROGRESS

PHASE 1

  • Structure is complete

  • Windows and doors have arrived on island and are being installed

  • Interior walls are in the process of being laid out

  • Ancillary works are progressing well

 
PHASE 2

  • Structure is now complete. Seventh level roof slab has been poured

  • Units 201 and 202 glass doors and windows are being installed

  • The staircase’s fire protection, electrical and plumbing works are roughed in up to the 7th floor level

  • The pool containment walls and slabs have been poured and propped for pool construction

  • MEP cans, block outs and sleeves are installed throughout

  • Ancillary works are progressing well

  • Unit 202 model room works are ongoing

  • All inspections for Unit 202 model room have been approved by BCU

 
PHASE 3

  • The southeast corner basement slab has been poured

  • Oil interceptor installed and plumbing works are completed in the pour area

  • Main panel conduits as well as some branch circuit conduits have been installed below slab in the pour areas

  • Floor drains and catch basins are in place and plumbing completed throughout

  • First floor southeast corner slab is being formed and will then be ready to be poured

  • First floor northwest corner slab is being formed and will then be ready to be poured

  • Ancillary works are progressing well around Phase 3 structure

  • MEP sleeves, block outs and cans have been installed throughout poured areas