Construction on the Kailani site continues to progress. The Phase 2 structure is now up to the fourth floor level and the team is presently concentrating on completing the Phase 3 basement. The fit out of the hotel’s model room has begun in which the MEP is currently being installed.

 
 

CONSTRUCTION PROGRESS

PHASE 1

  • The Phase 1 structure is complete. The windows have arrived on site and are awaiting installation

  • Construction of Phase 1’s concrete slab canopy over the entry doors (eyebrow) is formed and ready to pour

  PHASE 2

  • The third floor walls are now ready to be poured

  • Staircase walls have been poured up to the fourth floor level

  • The staircase’s mechanical, electrical and plumbing works are roughed in up to the fourth floor level

  • The model room is currently being stud framed

  • All common partition walls for the units have now been framed

 PHASE 3

  • Ramp 1’s ground floor slab in the north east corner is framed and ready to be inspected and poured

  • Ramp 2 is being prepped by backfilling, compacting and forming - in preparation for inspection and pour