Construction Update: June 2020

Claire Johnston
Construction Update: June 2020
 

CONSTRUCTION PROGRESS

 
 

PHASE 1

  • Underground services have been installed – electrical, irrigation, water and sewer lines

  • Staircase and ramp are ready to be poured

  • Footing poured in generator corner. North East corner boundary wall to be poured shortly

  • Window wells poured and backfilled up to 9’ mean sea level

PHASE 2

  • Excavation continues

  • Setting out for Phase 3 Part 1 completed

  • Footings starting to be poured