Construction Update: July 2020
CONSTRUCTION PROGRESS
PHASE 1
Staircase and ramp have been poured
Generator structure slab scheduled to be poured at 22’msl imminently
Boundary wall in North East corner has been poured
PHASE 2
Boundary wall from Phase 1 North East corner is continuing
Pre-cast man holes for geo wells 5, 6 and 7 have been lifted in
PHASE 3
Elevator pit is being excavated
Elevator pit rebar cage is being fabricated
Multiple footings have been poured
Basement wall has been poured to 6’msl
South East corner by Coral Sands sheet piled and deep well blown
De-watering drainage pond to assist with pouring of footings
National Roads Authority has completed crosswalks and signage on North Church Street