CONSTRUCTION PROGRESS

 
 

PHASE 1

  • Staircase and ramp have been poured

  • Generator structure slab scheduled to be poured at 22’msl imminently

  • Boundary wall in North East corner has been poured

PHASE 2

  • Boundary wall from Phase 1 North East corner is continuing

  • Pre-cast man holes for geo wells 5, 6 and 7 have been lifted in

PHASE 3

  • Elevator pit is being excavated

  • Elevator pit rebar cage is being fabricated

  • Multiple footings have been poured

  • Basement wall has been poured to 6’msl

  • South East corner by Coral Sands sheet piled and deep well blown

  • De-watering drainage pond to assist with pouring of footings

  • National Roads Authority has completed crosswalks and signage on North Church Street