Claire Johnston

Construction Update: September 2020

Claire Johnston
Construction Update: September 2020
 

Underground structural works are progressing well. Guest elevator footings are complete and service elevator is ready to be dug out. Foundations are well underway throughout Phase 3 and excavation has started on the south side of the site.

 
 

CONSTRUCTION PROGRESS

PHASE 2

  • Boundary wall from Phase 1 North East corner is poured and waterproofed around the north side of the property

  • Pre cast man holes for geo wells have been lifted in

  • Around the edge of the property we have been continuing running plumbing and electrical service lines into Phase 2

  • All the geo wells are installed

  • Lift station has been poured

PHASE 3

  • The month of August was mainly focused on the Guest Elevator Pit – it is the biggest, single footing of the project! (This meant lots and lots of water!)

  • Happy to report that the guest elevator pit has now been excavated, de-watered and the pad, footing and stem walls poured

  • Multiple footings have been poured

  • Basement wall has been poured to 6’msl

  • Sheet piles and deep wells have been blown on the South East corner

  • Excavation is well underway on the south side of the site, ready to start work on the Service Elevator pit